防腐工程地坪怎么施工
施工工艺:
Construction technology:
1、地面处理 : 依据地面状况做好打磨、修补、除污、除尘;
1. Ground treatment: grinding, repairing, decontamination and dust removal according to the ground condition;
2、环氧底漆 :采用渗透性及附着力特强底漆滚涂一道,增强表面附着力;
2. Epoxy primer: Roll one primer with strong penetration and adhesion to enhance surface adhesion;
3、玻纤铺设 :用玻纤布全面铺设一道;
3. Fiberglass Laying: Laying one piece of fiberglass cloth in an all-round way;
4、环氧砂浆 :将环氧双组份加入石英砂,用镘刀将其均匀涂布多道;
4. Epoxy mortar: Epoxy double component is added to quartz sand and uniformly coated with a trowel knife.
5、环氧腻子 :用环氧双组份加入适量腻子粉,用镘刀将其均匀涂布多道;
5. Epoxy putty: adding proper amount of putty powder with epoxy two-component, evenly coating it with trowel knife for multi-channel;
6、重防腐面漆:用重防腐面漆滚涂二至三道;
6. Heavy-duty anti-corrosive topcoat: Roll two or three coatings with heavy-duty anti-corrosive topcoat;
7、地坪投入使用时间:以250C为准,24小时后方可上人,72小时后方可重压,气温较低时,间隔时间需适度延长。
7. The time when the floor is put into use: 250C, 24 hours later, and 72 hours later, the pressure can be heavy. When the temperature is low, the interval time should be prolonged moderately.